Roadworks - Mandurah Road

  • Major infrastructure projects
  • Construction

Project summary

Roadworks will be taking place on Mandurah Road from Fifty Road to Safety Bay Road Baldivis.

We're upgrading a section of Mandurah Road to improve safety and reduce the number of head-on and rear end crashes. Work is scheduled to start on 29 April 2024 with an anticipated completion date of 19 July 2024. The roadworks include:

  • the construction of sealed shoulders on the eastern and western verges
  • installation of a 2m-wide raised median along the centre of the road
  • upgraded street lighting.

Please refer to the image below for the project location.

Aerial view of Mandurah Road with the area between Fifty Road and Safety Bay Road highlighted red.

Traffic Management

During construction, traffic management will be in effect as per the approved Traffic Management Plan. This will include directional lane closures and detours during certain construction stages. Mandurah Road will remain open for the duration of the works albeit with restricted access. The table below depicts the directional lane closures and the planned traffic management stages. The dates highlighted are the scheduled dates. Please note these are subject to change depending on site conditions and other unforeseen circumstances.

StageRoad closure
 Stage 1 - (29/04/2024 - 03/06/2024) Southbound lane - Directional closure and detours
 Stage 2 - (04/06/2024 - 28/06/2024) Northbound lane - Directional closure and detours
 Stage 3 - (01/07/2024 - 19/07/2024) Finishing / Median works / Directional closure northbound and detours

Detours

The image below shows the southbound lane closure detour.

 Map showing detough along Fifty Road to Baldivis Road then Safety Bay Road.

The image below shows the northbound lane closure detour.

Map showing detour along Safety Bay Road, then Baldivis Road, then Fifty Road.

The image below shows the detour route for heavy vehicles.

Map showing detour along Dixon Road and Ennis Ave.

The contractor undertaking the works is West Coast Profilers (WCP) Civil, alternatively you can contact the City on 9528 0333 or customer@rockingham.wa.gov.au for more information. 