Our Road Resurfacing Program 2026/2027 is underway to ensure a comfortable and safe road network within our City.

As part of our annual road maintenance program to ensure a comfortable and safe road network, we will be resurfacing specific sections of the road throughout the City. During these works, temporary traffic management will be in place, and some detours may be required. If possible, please consider using an alternative route to avoid delays.

Locations

We will be resealing the following locations:

StreetLocation descriptionSuburbStart DateFinish DateNight works times

Settlers Avenue

Safety Bay Road to Nancy Ally

Baldivis

1 November 2026

2 November 20267pm - 1am

Safety Bay Road

Malibu Road to Short Street

Safety Bay

8 November 2026

11 November 20267pm - 5am

Townsend Road

Broughton Way to Boon Court

Rockingham

10 November 2026

12 November 20267pm - 5am

Wellard Road

Mandurah Road to 350m east

East Rockingham

11 November 2026

14 November 20267pm - 5am

Mandurah Road

Dixon Road to Kulija Road

Rockingham

14 November 2026

21 November 20267pm - 5am

Work hours and dates are subject to weather conditions and contractor availability. Residents may experience temporary noise, dust and minor disruptions while these works are underway.

Afterhours Contact Details: Raph (WestCoast Profilers) 0461 433 881 or Richard (Downer EDI) 0418 669 695

General Safety Information

For your safety and the safety of our crews, please:

  • Follow all temporary traffic management and signage in the area
  • keep clear of work areas, machinery and construction vehicles
  • take extra care when walking, cycling or driving near the works
  • follow any directions provided by authorised traffic controllers or site personnel.

Location

Settlers Avenue, Baldivis
Share this page