DateClosed December 2025
-
ProgressCompleted
Scope of works
The existing boat ramp and associated timber holding jetty have come to the end of their effective design and operational life and will be demolished.
The reconstruction works will be a combination of marine and land-based construction and will include the following:
two new reinforced pre-cast concrete boat ramps
new centralised holding jetty
installation of improved holding jetty fender system
construction of new and improved rock armour scour protection
concrete abutment and concrete hardstand apron
construction of concrete access paths between boat ramp and car parks
new and improved functional driveway launching and retrieval opportunities
The facility will also include the construction of a new Personal Water Craft (PWC)/Jet ski launching/retrieval ramp and associated holding jetty to ensure improved safe launch and retrieval times for all recreational trailered vessels.
These works will be completed using land-based plant and machinery from the existing structures and the existing facilities will be closed during the construction period.
The City undertakes these works in accordance with State Agency Environmental and Aboriginal Heritage approvals and conditions for works within the marine park.
Project timeline
Works are currently scheduled to commence May 2026 with anticipated completion August 2026.
Funding
The project has been partly funded by the Department of Transport's Recreational Boating Facilities Scheme (RBFS).
Project updates
We are committed to keeping the community informed throughout all stages of the project and as such this page will be updated.
Other information
For all local navigation warnings and notices to marines (TNTM), visit Transport WA - Notices to Marinersopens in a new window.
Notice: Zero Tolerance for Abusive and Anti Social Behaviour
The City of Rockingham is committed to providing a safe and respectful environment for our staff, contractors and the wider community.
Abusive, aggressive or threatening behaviour towards City staff or contractors, whether in person, over the phone or in writing, will not be tolerated.
Any such behaviour will result in further action as appropriate. We thank you in advance for treating our staff with courtesy and respect.
Project timeline
-
DateMarch 2026
-
ProgressCompleted
-
DateMay 2026
-
ProgressNot Started
-
DateAnticipated August 2026
-
ProgressNot Started