Aqua Jetty Stage Two

  • Major infrastructure projects
  • Planning and design

Project summary

The Aqua Jetty will be expanded and improved to cater for population growth.

The Aqua Jetty facility will be refurbished and expanded to cater for our population growth and to improve access and amenity for the community.

Background

The need for a future expansion of the Aqua Jetty facility to service our forecast population was first identified through the completion of a 2010 needs and feasibility study.

In February 2018 the City completed an updated Aqua Jetty Needs Assessment and Feasibility Study that investigated the capacity of the current facilities at the Aqua Jetty to meet the current and forecast community need. The study considered community and membership consultation and concluded that improvements and upgrades were required to both the aquatic and dry infrastructure to best cater for increased demand and ensure the Aqua Jetty continued to deliver as the City's flagship aquatic and leisure facility.

The Aqua Jetty currently includes a heated 50m outdoor pool, heated 25m indoor pool, leisure pool, hydrotherapy pool, sauna, fully-equipped health club, one multipurpose indoor court, outdoor courts, crèche and café.

The Aqua Jetty Stage 2 project will feature accessibility improvements throughout the facility including the development of new larger hydrotherapy pool as well as spa, sauna and steam room spaces, modernised change rooms, new and larger spaces for health and fitness programs including a larger gymnasium and two large group fitness rooms and a new spin class room. The development will also provide additional space for swimming programs at the facility will include an expanded learn to swim pool, and revised water play areas including two water slides and a water/splash pad play area.

Project update

August/September 2022 update

  • Final updates to schematic design nearing completion

Completed works

  • Community consultation completed December 2021
  • Concept design endorsed by Council February 2022

Project timeline

Design Phase
  • Date
    April 2021
  • Progress
    In progress
Community Consultation
  • Date
    December 2021
  • Progress
    Completed
Construction
  • Date
    2023/2024
  • Progress
    Not started
Open
  • Date
    2024/2025
  • Progress
    Not started

Concept plans

  • Artist impression only. Final design may differ.
  • Artist impression only. Final design may differ.
  • Artist impression only. Final design may differ.
  • Artist impression only. Final design may differ.
  • Artist impression only. Final design may differ.
  • Artist impression only. Final design may differ.
  • Aqua Jetty site concept plan - Actual build may differ
  • Aqua Jetty site concept plan - Actual build may differ
  • Aqua Jetty site concept plan - Actual build may differ
  • Artist impression only. Final design may differ.
  • Artist impression only. Final design may differ.
  • Artist impression only. Final design may differ.
  • Artist impression only. Final design may differ.
Previous ImageNext Image

Location

87 Warnbro Sound Avenue, Warnbro
Go to Top of the page