White Hart Lane Reserve Drainage Upgrade

  • Repairs and roadworks
  • Temporary works

Project summary

An additional drainage pit and Gross Pollutant Trap is being installed at the reserve.

The installation of an additional drainage pit at the St James Drive/Wollomai Road intersection and new Gross Pollutant Traps (GPTs) in the adjacent reserve is complete. GPTs are underground drainage structures that use physical processes to trap solid waste such as litter and coarse sediment.

The reinstatement of reticulation is complete, however the area where new turf is to be laid will be used as a temporary lay-down area for materials for works within the adjacent dog park.

The anticipated completion date for the reinstatement of the turf is early to mid November 2019.