Project summary

We've constructed a 100m extension of the Mersey Point Granite Seawall.

The construction of Mersey Point Granite Seawall’s 100m extension commenced in early April 2022 and was completed in June 2022.

The works involved:

  • Demolition and removal of the existing limestone seawall.
  • Earthworks associated with limestone seawall demolition and granite seawall construction.
  • Construction of a 100m granite seawall.
  • Footpath reconstruction.
  • Foreshore fence installation.
  • Mulching.

Works were completed from the beach and above the seawall at road level along Arcadia Drive, Shoalwater. Arcadia Drive between Mersey Road and Penguin Road had periods of closure during construction requiring traffic management.

For more information, please contact customer@rockingham.wa.gov.au.