Mersey Point Jetty Works Have Commenced

20/09/2017

Construction of Mersey Point Jetty has begun this month.

The City has commenced works for the construction of Mersey Point Jetty located in Shoalwater. The Marine Civil Contractor undertaking the works is SMC Marine.

Site possession was issued to the contractor on Tuesday, 12 September 2017. Site preparation has commenced including procurement of jetty materials and construction of the sand pad/coffer dam. The 32 x 24 m steel piles and 2 x 12 m steel fender piles were delivered to site on 13 September 2017. Pile driving will commence the week following the public holiday, Tuesday, 26 September 2017.

The estimated time for the jetty construction completion is 30 January 2018.